Photo depicts bulldozers placing fill in the south-west corner of the storage area, to the final elevation of 28.5 ft. View is looking north-east at storage area of hydraulic fill.
Photo depicts bulldozers placing fill in the south-west corner of the storage area, to the final elevation of 28.5 ft. View is looking north-east at storage area of hydraulic fill.
Notes
Title based on content of photograph. Alcan Collection 79.31.7
Photo depicts workers excavating for the construction of the alumina storage building.
Notes
Title based on content of photograph. -- Alcan ID No. BC-2-451. -- Sloping sides avoided cave-ins. -- Hal Whiting was Project Manager, Kitimat Constructors, for smelter and town construction. Hal Whiting Collection 985.65.267
Photo depicts a group of men concerned with the caisson dock construction. From left is Messrs., Cam Jenkinson, George Malby, McCallum, Hal Whiting, J. B. Whitton, S. T. Wynne-Jones, Van Houten and Dick Hermann. View is of three floating caissons that were being towed into position for sinking, creating the smelter dock.
Photo depicts a group of men concerned with the caisson dock construction. From left is Messrs., Cam Jenkinson, George Malby, McCallum, Hal Whiting, J. B. Whitton, S. T. Wynne-Jones, Van Houten and Dick Hermann. View is of three floating caissons that were being towed into position for sinking, creating the smelter dock.
Notes
Title based on content of photograph. -- Alcan ID No. BC-2-362. -- Messrs. Jenkinson, Wynne-Jones, and Hermann all work for Alcan Engineering under the Resident Engineer George Malby. Messrs. J.B. Whitton and Van Houten work for the consulting firm of Frederick R. Harris & Co. of New York, N.Y. Hal Whiting was Project Manager, Kitimat Constructors, for smelter and town construction. Hal Whiting Collection 985.65.212
Photo depicts Kitimat Constructors Project Manager Hal Whiting on right, standing beside a unidentified man. Both watch the construction activity occurring down on the tidal flats in front of them, site for the smelter.
Photo depicts Kitimat Constructors Project Manager Hal Whiting on right, standing beside a unidentified man. Both watch the construction activity occurring down on the tidal flats in front of them, site for the smelter.
Notes
Title based on content of photograph. -- Photographed by the International Harvester Company, manufacturers of construction equipment purchased for the Project. Hal Whiting Collection 985.65.99
Photo depicts the dredge and dragline excavating the channel from the dock to deep water, a truck dumping gravel for the foundation blanket into the bottom of a dump scow. The view looks toward the construction site for the permanent wharf from the south dike of the graving dock, crew bunkhouses of Smeltersite in the background.
Photo depicts the dredge and dragline excavating the channel from the dock to deep water, a truck dumping gravel for the foundation blanket into the bottom of a dump scow. The view looks toward the construction site for the permanent wharf from the south dike of the graving dock, crew bunkhouses of Smeltersite in the background.
Notes
Title based on content of photograph. -- Alcan ID No. BC-2-320. Hal Whiting Collection 985.65.211