Smelter Site looking East. Precast yard and storage in foreground. Structural steel being erected in Service Buildings. Forms being placed for Building 153 and Rectifier Building 102. Trucks dumping backfill behind. Burning in Townsite Area left background.
Smelter Site looking East. Precast yard and storage in foreground. Structural steel being erected in Service Buildings. Forms being placed for Building 153 and Rectifier Building 102. Trucks dumping backfill behind. Burning in Townsite Area left background.
Photo showing smeltersite looking east showing progress of structural steel and aluminum cladding in potline 2 and concrete footings and pot recess flours in potline 1. Service Building, roofs are completed, substation and precast yard and storage in foreground.
Photo showing smeltersite looking east showing progress of structural steel and aluminum cladding in potline 2 and concrete footings and pot recess flours in potline 1. Service Building, roofs are completed, substation and precast yard and storage in foreground.