Flood looking upstream of Neighbourhood C Drainage Canal from approx. station 25/00. Note silt etc. in canal. Section of canal in immediate foreground was cut to shape just prior to the flood.
Flood looking upstream of Neighbourhood C Drainage Canal from approx. station 25/00. Note silt etc. in canal. Section of canal in immediate foreground was cut to shape just prior to the flood.
View looking northwest of pile driving operations for timber bridge across Road "N" in Neighbourhood "C". Note Townsite Contractors lumber storage yard in background.
View looking northwest of pile driving operations for timber bridge across Road "N" in Neighbourhood "C". Note Townsite Contractors lumber storage yard in background.
Photograph showing excavation being undertaken by Sagimat for temporary Septic Tank, being installed near intersection of Kuldo Blvd. and Drainage Canal in Kildala Neighbourhood (C).
Photograph showing excavation being undertaken by Sagimat for temporary Septic Tank, being installed near intersection of Kuldo Blvd. and Drainage Canal in Kildala Neighbourhood (C).
Saska River Bridge. Length overall 177 feet, clear span 67 feet built by Survey Party in 2 1/2 days. 100 horses and mules crossed the following morning. Current 10 miles per hour.
Saska River Bridge. Length overall 177 feet, clear span 67 feet built by Survey Party in 2 1/2 days. 100 horses and mules crossed the following morning. Current 10 miles per hour.
Saskwa River Bridge. Length over all 177 feet, clear span 67 feet. Built by Survey Party in 2 1/2 days. 100 horses and mules crossed the following morning. Current 10 miles per hour.
Saskwa River Bridge. Length over all 177 feet, clear span 67 feet. Built by Survey Party in 2 1/2 days. 100 horses and mules crossed the following morning. Current 10 miles per hour.