Photo depicts bulldozers placing fill in the south-west corner of the storage area, to the final elevation of 28.5 ft. View is looking north-east at storage area of hydraulic fill.
Photo depicts bulldozers placing fill in the south-west corner of the storage area, to the final elevation of 28.5 ft. View is looking north-east at storage area of hydraulic fill.
Notes
Title based on content of photograph. Alcan Collection 79.31.7
Photo depicts Kitimat Constructors Project Manager Hal Whiting on right, standing beside a unidentified man. Both watch the construction activity occurring down on the tidal flats in front of them, site for the smelter.
Photo depicts Kitimat Constructors Project Manager Hal Whiting on right, standing beside a unidentified man. Both watch the construction activity occurring down on the tidal flats in front of them, site for the smelter.
Notes
Title based on content of photograph. -- Photographed by the International Harvester Company, manufacturers of construction equipment purchased for the Project. Hal Whiting Collection 985.65.99
Photo depicts workers excavating for the construction of the alumina storage building.
Notes
Title based on content of photograph. -- Alcan ID No. BC-2-451. -- Sloping sides avoided cave-ins. -- Hal Whiting was Project Manager, Kitimat Constructors, for smelter and town construction. Hal Whiting Collection 985.65.267
Photo depicts an aerial view of the smeltersite main camp showing married quarters, sternwheeler Delta King, hydraulic fill in progress, recreation building, hospital, power plant, sawmill and water tank.
Photo depicts an aerial view of the smeltersite main camp showing married quarters, sternwheeler Delta King, hydraulic fill in progress, recreation building, hospital, power plant, sawmill and water tank.
Notes
Title based on content of photograph. -- Alcan ID Numbers BC-2-243 and ACM-24311. Alcan Collection 78.11.32