Photograph of looking south east at the service buildings showing structural steel complete except for a few minor members. Lots of snow on ground, and man on the right is walking through the snow.
Bud Powell is a longtime resident of Kitimat and former smeltersite resident. He worked for Alcan.
Custodial History
Donated by Bud Powell.
Scope and Content
Photograph of looking south east at the service buildings showing structural steel complete except for a few minor members. Lots of snow on ground, and man on the right is walking through the snow.
Photo showing view looking west at bridge showing Kitimat River at Elevation 45, Centre Pier of pernament bridge at right with framework ready for final concrete pour.
Photo showing view looking west at bridge showing Kitimat River at Elevation 45, Centre Pier of pernament bridge at right with framework ready for final concrete pour.
Jamieson came to Kitimat from Vancouver to work on the Alcan project in 1952. With his first pay cheque he bought a small "Pony Kodak" camera at the local store (Hudson Bay?), and started taking coloured slides of the Kitimat from 1952-1953. Left Kitimat at the end of August 1953 to move to Montreal.
Jamieson came to Kitimat from Vancouver to work on the Alcan project in 1952. With his first pay cheque he bought a small "Pony Kodak" camera at the local store (Hudson Bay?), and started taking coloured slides of the Kitimat from 1952-1953. Left Kitimat at the end of August 1953 to move to Montreal.
Scope and Content
Slide of steel footings for potrooms 1 smeltersite.
Jamieson came to Kitimat from Vancouver to work on the Alcan project in 1952. With his first pay cheque he bought a small "Pony Kodak" camera at the local store (Hudson Bay?), and started taking coloured slides of the Kitimat from 1952-1953. Left Kitimat at the end of August 1953 to move to Montreal.
Scope and Content
Slide of steel footings. Disposal ramp in background.
Photo showing smeltersite looking east showing progress of structural steel and aluminum cladding in potline 2 and concrete footings and pot recess flours in potline 1. Service Building, roofs are completed, substation and precast yard and storage in foreground.
Photo showing smeltersite looking east showing progress of structural steel and aluminum cladding in potline 2 and concrete footings and pot recess flours in potline 1. Service Building, roofs are completed, substation and precast yard and storage in foreground.