Photograph of aerial view looking north at the plant site, with H.M.C.S. Sioux at the wharf. Tide elevation is approximately 2.5 feet, and the extent of the dredge cut in the harbour can be clearly seen.
Bill was one of the superintendents with Saguenay Kitimat.
Custodial History
Donated by Joanna Gallacher
Scope and Content
Photograph of aerial view looking north at the plant site, with H.M.C.S. Sioux at the wharf. Tide elevation is approximately 2.5 feet, and the extent of the dredge cut in the harbour can be clearly seen.
Photograph of view looking west at bridge site showing Kitimat River at elevation 45. Centre pier of permanent bridge at right with formwork for final concrete pour.
Bill was one of the superintendents with Saguenay Kitimat.
Custodial History
Donated by Joanna Gallacher
Scope and Content
Photograph of view looking west at bridge site showing Kitimat River at elevation 45. Centre pier of permanent bridge at right with formwork for final concrete pour.
Photograph of view of Kitimat River bridge looking west. East pier in foreground showing whalers in place with sheet piling driven to grade. Center pier-right-two bearingpiles driven to required bearing. Left-sixty foot pile in place for splicing. Temporary bridge-crew completing placing rock in pier.
Bill was one of the superintendents with Saguenay Kitimat.
Custodial History
Donated by Joanna Gallacher
Scope and Content
Photograph of view of Kitimat River bridge looking west. East pier in foreground showing whalers in place with sheet piling driven to grade. Center pier-right-two bearingpiles driven to required bearing. Left-sixty foot pile in place for splicing. Temporary bridge-crew completing placing rock in pier.
Smelter Site Looking East. Foreground, perforated Concrete Pipe for Ground Master Ditch. Middleground, Pre-cast Concrete Yard with Storage Stacks at right. Structural Steel partially complete in Service Buildings Lines D to M. Footings for Pot Line 2 at right.
Smelter Site Looking East. Foreground, perforated Concrete Pipe for Ground Master Ditch. Middleground, Pre-cast Concrete Yard with Storage Stacks at right. Structural Steel partially complete in Service Buildings Lines D to M. Footings for Pot Line 2 at right.
Smelter Site looking East. Precast yard and storage in foreground. Structural steel being erected in Service Buildings. Forms being placed for Building 153 and Rectifier Building 102. Trucks dumping backfill behind. Burning in Townsite Area left background.
Smelter Site looking East. Precast yard and storage in foreground. Structural steel being erected in Service Buildings. Forms being placed for Building 153 and Rectifier Building 102. Trucks dumping backfill behind. Burning in Townsite Area left background.
Smelter Site looking East. K. C. Administration Building left foreground. Ground water ditch in front of pre-cast Concrete Yard. Service Building area behind with pre-cast panels in place for forge shop and warehouse. Fooding Forms and warehouse. Footing Forms prepared for Pot Room 2 C at right.
Smelter Site looking East. K. C. Administration Building left foreground. Ground water ditch in front of pre-cast Concrete Yard. Service Building area behind with pre-cast panels in place for forge shop and warehouse. Fooding Forms and warehouse. Footing Forms prepared for Pot Room 2 C at right.