Photograph of aerial view of west end of neighbourhood C-I and motel site A. Please note temporary housing units in left centre of photograph. Clearing shown in lower left corner is that for neighbourhood C Dyke.
Donated by Jackie Worboys. Given to the Jackie Mufford Worboys family by Wally Melville.
Scope and Content
Photograph of aerial view of west end of neighbourhood C-I and motel site A. Please note temporary housing units in left centre of photograph. Clearing shown in lower left corner is that for neighbourhood C Dyke.
Photograph of the temporary housing site in neighbourhood C-1. Note the sections of the 210 units arriving in the building area. Crane at work on left.
Donated by Jackie Worboys. Given to the Jackie Mufford Worboys family by Wally Melville.
Scope and Content
Photograph of the temporary housing site in neighbourhood C-1. Note the sections of the 210 units arriving in the building area. Crane at work on left.
Photograph of view of the 11 man bunkhouses at the back of the motel site. Roofing is now being placed. These are prefab. units - went up in 6 days from dockside. Logs are laid in the foreground.
Donated by Jackie Worboys. Given to the Jackie Mufford Worboys family by Wally Melville.
Scope and Content
Photograph of view of the 11 man bunkhouses at the back of the motel site. Roofing is now being placed. These are prefab. units - went up in 6 days from dockside. Logs are laid in the foreground.
Looking north from sandhill (elev. 640 +) to site of permanent bridge center left, Townsite camp center right edge of photo, and Townsite ridge left to right.
Looking north from sandhill (elev. 640 +) to site of permanent bridge center left, Townsite camp center right edge of photo, and Townsite ridge left to right.
Smelter Site Looking East. Foreground, perforated Concrete Pipe for Ground Master Ditch. Middleground, Pre-cast Concrete Yard with Storage Stacks at right. Structural Steel partially complete in Service Buildings Lines D to M. Footings for Pot Line 2 at right.
Smelter Site Looking East. Foreground, perforated Concrete Pipe for Ground Master Ditch. Middleground, Pre-cast Concrete Yard with Storage Stacks at right. Structural Steel partially complete in Service Buildings Lines D to M. Footings for Pot Line 2 at right.