Photo depicts the permanent Kemano townsite at Camp No. 5. View is looking towards beach. Seen on the left are permanent homes for powerhouse staff. On the right are the temporary buildings known as quonset huts used during the construction years as crew quarters.
Photo depicts the permanent Kemano townsite at Camp No. 5. View is looking towards beach. Seen on the left are permanent homes for powerhouse staff. On the right are the temporary buildings known as quonset huts used during the construction years as crew quarters.
Notes
Title based on content of photograph. -- Alcan ID No. 2KR-298. -- Permanent housing construction began in 1957. Alcan Collection
Photograph of an aerial of the Alcan Smelter and area. Moon Bay area and surrounding service roads are in the front on the left. Estuary is on the right of the Smelter further back. Townsite is beyond that. View extends into mountain ranges of the valley. Sky is cloudy.
Photograph of an aerial of the Alcan Smelter and area. Moon Bay area and surrounding service roads are in the front on the left. Estuary is on the right of the Smelter further back. Townsite is beyond that. View extends into mountain ranges of the valley. Sky is cloudy.
Photo showing 7 international L-190 trucks, complete with Jaegar ReadyMix Concrete Machines, first installment of a large fleet at Kitimat. In early June, these were waiting for completion of batching plant installation. They were used to carry concrete directly to the new smelter, townsite or any construction in progress. Batch plant location is at Gravel Mountain.
Photo showing 7 international L-190 trucks, complete with Jaegar ReadyMix Concrete Machines, first installment of a large fleet at Kitimat. In early June, these were waiting for completion of batching plant installation. They were used to carry concrete directly to the new smelter, townsite or any construction in progress. Batch plant location is at Gravel Mountain.
Smelter Site looking East. Precast yard and storage in foreground. Structural steel being erected in Service Buildings. Forms being placed for Building 153 and Rectifier Building 102. Trucks dumping backfill behind. Burning in Townsite Area left background.