Photo depicts a view of Minette Bay scow grid with two barges being unloaded. The left barge is loaded with Johnson Crooks materials and the right barge with Hullah Construction materials.
Photo depicts a view of Minette Bay scow grid with two barges being unloaded. The left barge is loaded with Johnson Crooks materials and the right barge with Hullah Construction materials.
Illustration depicts the extent of the Project, from the Kenney Dam and reservoir area to the transmission line and smelter. The future tunnel or the Kemano Completion Project is also included.
Illustration depicts the extent of the Project, from the Kenney Dam and reservoir area to the transmission line and smelter. The future tunnel or the Kemano Completion Project is also included.
Notes
Illustration from Alcan's publication "Kitimat-Kemano, Five Years of Operation, 1954-1959". Alcan Collection
Photo depicts a unidentified man sitting on the Nechako River bank watching the the activities of construction of the dam at the canyon. Right bank stripping and left bank tunnel haul road shown.
Photo depicts a unidentified man sitting on the Nechako River bank watching the the activities of construction of the dam at the canyon. Right bank stripping and left bank tunnel haul road shown.
Notes
Title based on content of photo. -- A rock dam was chosen for its ability to withstand earthquakes. Morrison-Knudsen Company Collection
Photo depicts a International diesel TD-24 spreading a layer of large stones at the base of the Nechako Dam.
Notes
ID no. C 5927. -- Title based on content of photo. -- These layers of various size rock stone and clay will all slope towards the rock fill at about a 45 degree pitch. Official naming ceremony renamed dam the Kenney Dam. Hal Whiting Collection 985.65.56
Negatives showing the Nechako Reservoir, the Kenney Dam, & the Skins Lake Spillway which were built to create hydroelectric power to be used by the Alcan aluminum smelter in Kitimat. Also pictured is Des Lake, Alcan barge Tahtsa II at East Tahtsa, a view of the Entiako River as it enters the Nechako Reservoir, an underwater cutting barge, & Eurocan's logging operation at Andrews Bay on Ootsa Lake.
Negatives showing the Nechako Reservoir, the Kenney Dam, & the Skins Lake Spillway which were built to create hydroelectric power to be used by the Alcan aluminum smelter in Kitimat. Also pictured is Des Lake, Alcan barge Tahtsa II at East Tahtsa, a view of the Entiako River as it enters the Nechako Reservoir, an underwater cutting barge, & Eurocan's logging operation at Andrews Bay on Ootsa Lake.