Smelter Site Looking East. Foreground, perforated Concrete Pipe for Ground Master Ditch. Middleground, Pre-cast Concrete Yard with Storage Stacks at right. Structural Steel partially complete in Service Buildings Lines D to M. Footings for Pot Line 2 at right.
Smelter Site Looking East. Foreground, perforated Concrete Pipe for Ground Master Ditch. Middleground, Pre-cast Concrete Yard with Storage Stacks at right. Structural Steel partially complete in Service Buildings Lines D to M. Footings for Pot Line 2 at right.
Photo showing Carbon Paste Plant area looking north-east showing progress of deep foundations and start of building footings, compressor foundation and column footings for compressor building 140 in foreground.
Photo showing Carbon Paste Plant area looking north-east showing progress of deep foundations and start of building footings, compressor foundation and column footings for compressor building 140 in foreground.