Smelter Site Looking East. Foreground, perforated Concrete Pipe for Ground Master Ditch. Middleground, Pre-cast Concrete Yard with Storage Stacks at right. Structural Steel partially complete in Service Buildings Lines D to M. Footings for Pot Line 2 at right.
Smelter Site Looking East. Foreground, perforated Concrete Pipe for Ground Master Ditch. Middleground, Pre-cast Concrete Yard with Storage Stacks at right. Structural Steel partially complete in Service Buildings Lines D to M. Footings for Pot Line 2 at right.
Photograph looking downstream from the west side of the park near the Kitimat River Bridge showing river within 1' of maximum flood on Nov. 3. Note boom of dragline in centre of picture.
Photograph looking downstream from the west side of the park near the Kitimat River Bridge showing river within 1' of maximum flood on Nov. 3. Note boom of dragline in centre of picture.