Photo depicts the welcome sign for Kitimat on the wharf that greeted all workers to the Kitimat Project upon their arrival by boat.
Notes
Title based on content of photograph. -- Hal Whiting was Project Manager, Kitimat Constructors, for smelter and town construction. Hal Whiting Collection 985.65.113
Photocopied documents relating to John McLachlan's employment with Alcan.
1) Letter of employment, G. W. Whitehead (Alcan) to John McLachlan, offering position as Draughtsman in Kitimat. April 10th 1953
2) Letter of acceptance, John McLachlan to G.W. Whitehead. April 11th 1953
3) Alcan Personnel Department introduction form, to Mr. G. T. Malby, Resident Engineer, May 13th 1953
4) Invitation to join Retirement Income and Life Insurance Plan, Ian Maclean to John McLachlan, June 23rd 1954.
5) Account of duties as Senior Draughtsman, John McLachlan to W. H. Sparks, September 11th 1956.
John McLachlan arrived in Kitimat in 1953 as a 23-year-old immigrant and went on to work at Alcan's Property Engineering Department for almost 40 years. He started out as a land surveyor and cartographer in the town's early years and ended his career as a Senior Legal Draftsmen.
Custodial History
Donated by Jean Lunny, January 12th 2018
Scope and Content
Photocopied documents relating to John McLachlan's employment with Alcan.
1) Letter of employment, G. W. Whitehead (Alcan) to John McLachlan, offering position as Draughtsman in Kitimat. April 10th 1953
2) Letter of acceptance, John McLachlan to G.W. Whitehead. April 11th 1953
3) Alcan Personnel Department introduction form, to Mr. G. T. Malby, Resident Engineer, May 13th 1953
4) Invitation to join Retirement Income and Life Insurance Plan, Ian Maclean to John McLachlan, June 23rd 1954.
5) Account of duties as Senior Draughtsman, John McLachlan to W. H. Sparks, September 11th 1956.
Photograph of construction of service buildings looking south, showing roof of passageway #151 in left foreground, building #153, office and lunch building in right foreground, and pot room 2C structural steel in background.
Bud Powell is a longtime resident of Kitimat and former smeltersite resident. He worked for Alcan.
Custodial History
Donated by Bud Powell.
Scope and Content
Photograph of construction of service buildings looking south, showing roof of passageway #151 in left foreground, building #153, office and lunch building in right foreground, and pot room 2C structural steel in background.
Photograph of view looking east showing progress of potline 2, alumina storage bins and sub-station 2. Area under construction, construction material in foreground.
Bud Powell is a longtime resident of Kitimat and former smeltersite resident. He worked for Alcan.
Custodial History
Donated by Bud Powell.
Scope and Content
Photograph of view looking east showing progress of potline 2, alumina storage bins and sub-station 2. Area under construction, construction material in foreground.
Photo depicts workers excavating for the construction of the alumina storage building.
Notes
Title based on content of photograph. -- Alcan ID No. BC-2-451. -- Sloping sides avoided cave-ins. -- Hal Whiting was Project Manager, Kitimat Constructors, for smelter and town construction. Hal Whiting Collection 985.65.267
Photograph of Public Works Building under construction in the Service Centre. Scaffolding still up. Cinderblocks piled on scaffolding and ground. Sign for public works building and Northwest Construction is leaning on the right side.
Donated by Jackie Worboys. Given to the Jackie Mufford Worboys family by Wally Melville.
Scope and Content
Photograph of Public Works Building under construction in the Service Centre. Scaffolding still up. Cinderblocks piled on scaffolding and ground. Sign for public works building and Northwest Construction is leaning on the right side.
Photograph of view looking east in the first stage area of potlines 6-10, showing stripping operation progressing despite snow conditions. Crane loading material into truck in centre.
Bud Powell is a longtime resident of Kitimat and former smeltersite resident. He worked for Alcan.
Custodial History
Donated by Bud Powell.
Scope and Content
Photograph of view looking east in the first stage area of potlines 6-10, showing stripping operation progressing despite snow conditions. Crane loading material into truck in centre.
Photograph of asphalt paving being placed on the Service Centre road between the Public Works building and the railway. Seven men visible working. Sandhill in background on the right.
Donated by Jackie Worboys. Given to the Jackie Mufford Worboys family by Wally Melville.
Scope and Content
Photograph of asphalt paving being placed on the Service Centre road between the Public Works building and the railway. Seven men visible working. Sandhill in background on the right.
Photograph of view looking south showing excavation to elevation 54 in potline 9 area. Area is cleared with machinery working. Potlines visible in background.
Bud Powell is a longtime resident of Kitimat and former smeltersite resident. He worked for Alcan.
Custodial History
Donated by Bud Powell.
Scope and Content
Photograph of view looking south showing excavation to elevation 54 in potline 9 area. Area is cleared with machinery working. Potlines visible in background.
Photograph of aerial view looking west toward potline group B. Note sewer installed on cast side of terminal railway opposite potroom 8B. Storage area in foreground.
Bud Powell is a longtime resident of Kitimat and former smeltersite resident. He worked for Alcan.
Custodial History
Donated by Bud Powell.
Scope and Content
Photograph of aerial view looking west toward potline group B. Note sewer installed on cast side of terminal railway opposite potroom 8B. Storage area in foreground.