Smelter Site looking East. Precast yard and storage in foreground. Structural steel being erected in Service Buildings. Forms being placed for Building 153 and Rectifier Building 102. Trucks dumping backfill behind. Burning in Townsite Area left background.
Smelter Site looking East. Precast yard and storage in foreground. Structural steel being erected in Service Buildings. Forms being placed for Building 153 and Rectifier Building 102. Trucks dumping backfill behind. Burning in Townsite Area left background.
Photograph of aerial view of alumina storage area looking west and showing surcharge in stage 1 position. Note new scow grid and salt water pumphouse in foreground.
Bud Powell is a longtime resident of Kitimat and former smeltersite resident. He worked for Alcan.
Custodial History
Donated by Bud Powell.
Scope and Content
Photograph of aerial view of alumina storage area looking west and showing surcharge in stage 1 position. Note new scow grid and salt water pumphouse in foreground.
Photo depicts workers excavating for the construction of the alumina storage building.
Notes
Title based on content of photograph. -- Alcan ID No. BC-2-451. -- Sloping sides avoided cave-ins. -- Hal Whiting was Project Manager, Kitimat Constructors, for smelter and town construction. Hal Whiting Collection 985.65.267
Alcan smelter employees returning to work after layoffs due to plant shut down caused by a rock slide in Kemano tunnel. (Rock Fall in the Kemano Power tunnel 65' long, 140' high, and 125 cubic yards of material) cut off power to Kitimat plant. Only after a dewatering of the tunnel, was power restored.
Alcan smelter employees returning to work after layoffs due to plant shut down caused by a rock slide in Kemano tunnel. (Rock Fall in the Kemano Power tunnel 65' long, 140' high, and 125 cubic yards of material) cut off power to Kitimat plant. Only after a dewatering of the tunnel, was power restored.
Photograph of view looking east showing progress of potline 2, alumina storage bins and sub-station 2. Area under construction, construction material in foreground.
Bud Powell is a longtime resident of Kitimat and former smeltersite resident. He worked for Alcan.
Custodial History
Donated by Bud Powell.
Scope and Content
Photograph of view looking east showing progress of potline 2, alumina storage bins and sub-station 2. Area under construction, construction material in foreground.
Smelter Site Looking East. Foreground, perforated Concrete Pipe for Ground Master Ditch. Middleground, Pre-cast Concrete Yard with Storage Stacks at right. Structural Steel partially complete in Service Buildings Lines D to M. Footings for Pot Line 2 at right.
Smelter Site Looking East. Foreground, perforated Concrete Pipe for Ground Master Ditch. Middleground, Pre-cast Concrete Yard with Storage Stacks at right. Structural Steel partially complete in Service Buildings Lines D to M. Footings for Pot Line 2 at right.