Photo depicts the Prepakt aggregate conveyor in foreground during operations at elbow (seen in distance), Elevation 210'. View is looking upstream along No. 2 penstock.
Photo depicts the Prepakt aggregate conveyor in foreground during operations at elbow (seen in distance), Elevation 210'. View is looking upstream along No. 2 penstock.
Notes
Alcan ID no. 5793. -- Penstock No. 2 was completed after the smelter had started aluminum production in 1954 with Penstock No. 1. Alcan Collection
Photo depicts the world record setting swing shift miners at the Horetzky-Kemano heading, posing on the Copco drill set-up with a sign that gives specifics to their record.
Photo depicts the world record setting swing shift miners at the Horetzky-Kemano heading, posing on the Copco drill set-up with a sign that gives specifics to their record.
Notes
Alcan ID no. KR-771. -- The project introduced a new breed of miner, the construction miner. Alcan Collection
Photo depicts a worker looking up at a sign above the entrance to the recreation hall that reads, "Tunnel target, give them both barrels Tahtsa." The sign was a target date for the two ends of the tunnel to meet September 1st.
Photo depicts a worker looking up at a sign above the entrance to the recreation hall that reads, "Tunnel target, give them both barrels Tahtsa." The sign was a target date for the two ends of the tunnel to meet September 1st.
Photo depicts men on the tramway used for moving equipment and workers up the mountain. View is looking down on the Kemano Valley. Depicted lowering penstock liner.
Photo depicts men on the tramway used for moving equipment and workers up the mountain. View is looking down on the Kemano Valley. Depicted lowering penstock liner.
Photo depicts a miner beside the penstock liner which is being lowered from the 2600' level.
Notes
Alcan ID no. KR-1386. -- Note the bridle assembly. -- Liners were lowered on a dolly on a 140-ton hoist, then transferred to skid rails for the final journey. Alcan Collection
Photo depicts two welders, welding the penstock liner elbow section to the 1600' level.
Notes
Alcan ID no. KR-1166. -- Electric pre-heaters used to bring steel up to required temperature prior to and throughout the welding operation. Alcan Collection
Photo depicts the aggregate stockpile at Horetzky, being built up to a total of 120,000 cubic yards for the power tunnel lining. View is looking south from the top of the batch plant.
Photo depicts the aggregate stockpile at Horetzky, being built up to a total of 120,000 cubic yards for the power tunnel lining. View is looking south from the top of the batch plant.
Photo depicts project management meeting for the symbolic throwing of the switch for tunnel breakthrough. Present from left are Mr. Madsen, M.K. Assistant Project Manager; Mr. Franklin Matthias, Alcan Assistant Project Manager; Mr. Reed, M.K. Area Engineer; Mr. Percy E. Radley, Alcan Project Manager; Mr. Roestad, Alcan Resident Engineer; Mr. Whitey Davis, M.K. General Underground Superintendent; Mr. McNeely Dubose, Alcan Vice President, seen here ready to throw the switch; Mr. V. Rland, M.K Superintendent at Horetzky.
Photo depicts project management meeting for the symbolic throwing of the switch for tunnel breakthrough. Present from left are Mr. Madsen, M.K. Assistant Project Manager; Mr. Franklin Matthias, Alcan Assistant Project Manager; Mr. Reed, M.K. Area Engineer; Mr. Percy E. Radley, Alcan Project Manager; Mr. Roestad, Alcan Resident Engineer; Mr. Whitey Davis, M.K. General Underground Superintendent; Mr. McNeely Dubose, Alcan Vice President, seen here ready to throw the switch; Mr. V. Rland, M.K Superintendent at Horetzky.
Notes
Alcan ID no. KR-1499. -- M.K. refers to Morrison-Knudsen Company, contractor for the Project. Alcan Collection