Photo depicts the permanent Kemano townsite at Camp No. 5. View is looking towards beach. Seen on the left are permanent homes for powerhouse staff. On the right are the temporary buildings known as quonset huts used during the construction years as crew quarters.
Photo depicts the permanent Kemano townsite at Camp No. 5. View is looking towards beach. Seen on the left are permanent homes for powerhouse staff. On the right are the temporary buildings known as quonset huts used during the construction years as crew quarters.
Notes
Title based on content of photograph. -- Alcan ID No. 2KR-298. -- Permanent housing construction began in 1957. Alcan Collection
Photo depicts a unidentified man sitting on the Nechako River bank watching the the activities of construction of the dam at the canyon. Right bank stripping and left bank tunnel haul road shown.
Photo depicts a unidentified man sitting on the Nechako River bank watching the the activities of construction of the dam at the canyon. Right bank stripping and left bank tunnel haul road shown.
Notes
Title based on content of photo. -- A rock dam was chosen for its ability to withstand earthquakes. Morrison-Knudsen Company Collection
Photo depicts a tent with flat-top house assembly on a production line in West Vancouver for Johnson-Crooks Construction Corporation.
Notes
Title based on content of photograph. -- Slide No. 40 -- The circus tent assembly line was erected at Vancouver Tug and Barge below the Lion's Gate Bridge. Temporary housing destined for Kitimat was assembled there in three sections, then barged to Kitimat - 10 houses or 30 sections on each barge. -- Electrician Bill Frahler wired approximately 2,000 houses in Kitimat camps and townsite between 1954 and 1958, working first for Johnson-Crooks then Straits Construction, both U.S. contractors. Bill Frahler Collection 2003.32