Photo depicts a an International truck heading to Horetzky Creek Camp on the Horetzky Valley Road.
Notes
Morrison-Knudsen Company had several roads such as this one, constructed to get workers and equipment to the various work sites for tunnel construction. 985.65.80
Photo depicts an International truck heading to Horetzky Creek Camp on the Horetzky Valley Road.
Notes
Morrison-Knudsen Company had several roads such as this one, constructed to get workers and equipment to the various work sites for tunnel construction. 985.65.80
Photo depicts the men in charge of operations. From left is Vice President A.W. Whitaker Jr. seen sitting in a helicopter; Project Manager Percy E. Radley; Chief Resident Engineer John Kendrick. The three men are all taking a look at what could be a map.
Photo depicts the men in charge of operations. From left is Vice President A.W. Whitaker Jr. seen sitting in a helicopter; Project Manager Percy E. Radley; Chief Resident Engineer John Kendrick. The three men are all taking a look at what could be a map.
Illustration depicts a map of the Alcan project area, reaching from Prince Rupert to Kenney Dam. Seen is the transmission line, Kemano power plant and the lakes of the region.
Illustration depicts a map of the Alcan project area, reaching from Prince Rupert to Kenney Dam. Seen is the transmission line, Kemano power plant and the lakes of the region.
Notes
Clipping origin unknown. Fritz Wurster Collection. 2002.32
Photo depicts a worker with a double-headed axe on the Alcan Project posed at a waterfall located in the Kemano area.
Notes
Photographed by the International Harvester Company, manufacturers of construction equipment purchased for the Project. Hal Whiting Collection 985.65.76
Photo depicts a surveyor on the Alcan Project surveying and posed beside a waterfall located in the Kemano area.
Notes
Photographed by the International Harvester Company, manufacturers of construction equipment purchased for the Project. -- ID No. C6067. Hal Whiting Collection 985.65.79
Photo depicts an International TD-24 crawler dozing tunnel muck at the 2600' camp above the Kemano Valley.
Notes
ID No. C 6098. -- Title based on content of photo. -- The International Harvester Company, manufacturers of construction equipment such as this crawler purchased for the Project. Hal Whiting Collection 985.65.75
Image depicts a humorous reprieve certificate given to employees of the Alcan Project. The content also implies the hardships endured by the Morrison-Knudsen Company workers in Kemano.
Image depicts a humorous reprieve certificate given to employees of the Alcan Project. The content also implies the hardships endured by the Morrison-Knudsen Company workers in Kemano.
Notes
Title based on contents of text. Ernie Archer Collection
Photo depicts a International diesel TD-24 spreading a layer of large stones at the base of the Nechako Dam.
Notes
ID no. C 5927. -- Title based on content of photo. -- These layers of various size rock stone and clay will all slope towards the rock fill at about a 45 degree pitch. Official naming ceremony renamed dam the Kenney Dam. Hal Whiting Collection 985.65.56
Diagram depicts penstock number 1 and 2 showing elevations.
Notes
Penstock No. 2 was completed after the smelter had started aluminum production with Penstock No. 1. -- Tunnel No. 2 with penstocks No. 3 & 4 was the Kemano Completion Project which was cancelled in 1991. Morrison-Knudsen Company Collection
Photo depicts workers clearing the transmission line right-of-way. The smelter site preparation and smoke from the townsite clearing are in the distance.
Photo depicts workers clearing the transmission line right-of-way. The smelter site preparation and smoke from the townsite clearing are in the distance.
Notes
Title based on content of photograph. Alcan Collection Accession no. 73.3.10.1
Photo depicts the welcome sign for Kitimat on the wharf that greeted all workers to the Kitimat Project upon their arrival by boat.
Notes
Title based on content of photograph. -- Hal Whiting was Project Manager, Kitimat Constructors, for smelter and town construction. Hal Whiting Collection 985.65.113
Photo depicts an aerial view of the smeltersite main camp showing married quarters, sternwheeler Delta King, hydraulic fill in progress, recreation building, hospital, power plant, sawmill and water tank.
Photo depicts an aerial view of the smeltersite main camp showing married quarters, sternwheeler Delta King, hydraulic fill in progress, recreation building, hospital, power plant, sawmill and water tank.
Notes
Title based on content of photograph. -- Alcan ID Numbers BC-2-243 and ACM-24311. Alcan Collection 78.11.32
Photo depicts a barge loaded with muck dredged from the wharf area. The International TD-9 dozer boat on the barge was there to push loads off as the barge was moved along.
Photo depicts a barge loaded with muck dredged from the wharf area. The International TD-9 dozer boat on the barge was there to push loads off as the barge was moved along.
Notes
Title based on content of photograph. -- International Harvester Company ID No. C 6039. International Harvester Company manufacturerd construction equipment purchased for the Project. -- Dredging at the wharf area provided sufficient water space for large ships to dock. Muck was dumped onto these barges by the clamshell bucket and towed out to deep water. Hal Whiting Collection 985.65.123