Photograph of with the outer housing of the turbine in place, work proceeds with the installation of generator 8 in Alcan's Kemano Powerhouse, which will increase cpacity from the present 784,000 kilowatts to close to 98,000 kilowatts (1,200,000 H.P). The instillation of Generator 8 is being carried out by Mattias & Nicol, general contractors of Vancouver B.C. Employees of Canadian Westinghouse are now on site and are erecting the generator. Work began early in February with completion date for September.
Photograph of with the outer housing of the turbine in place, work proceeds with the installation of generator 8 in Alcan's Kemano Powerhouse, which will increase cpacity from the present 784,000 kilowatts to close to 98,000 kilowatts (1,200,000 H.P). The instillation of Generator 8 is being carried out by Mattias & Nicol, general contractors of Vancouver B.C. Employees of Canadian Westinghouse are now on site and are erecting the generator. Work began early in February with completion date for September.