Photo showing installation of the Screening Plant at Gravel Mountain almost complete on July 1st, each conveyor drops a seperate size stone directly over the enclosed conveyor belt on the ground. By opening the chutes visible on the top of the protective structure over the bet, any size stone can be selected for any purpose. Another conveyor, similiar to this will be installed at left, at a right angle to this one.
Photo showing installation of the Screening Plant at Gravel Mountain almost complete on July 1st, each conveyor drops a seperate size stone directly over the enclosed conveyor belt on the ground. By opening the chutes visible on the top of the protective structure over the bet, any size stone can be selected for any purpose. Another conveyor, similiar to this will be installed at left, at a right angle to this one.
Inscribed in pen: Survey Truck and me the stories I could tell on that canopy on back of truck they vould give me lumber - nails. Build one so I swipea A piano case - The Only one. R25-16
Photo depicts a an International truck heading to Horetzky Creek Camp on the Horetzky Valley Road.
Notes
Morrison-Knudsen Company had several roads such as this one, constructed to get workers and equipment to the various work sites for tunnel construction. 985.65.80
Photo depicts an International truck heading to Horetzky Creek Camp on the Horetzky Valley Road.
Notes
Morrison-Knudsen Company had several roads such as this one, constructed to get workers and equipment to the various work sites for tunnel construction. 985.65.80
Photo showing 7 international L-190 trucks, complete with Jaegar ReadyMix Concrete Machines, first installment of a large fleet at Kitimat. In early June, these were waiting for completion of batching plant installation. They were used to carry concrete directly to the new smelter, townsite or any construction in progress. Batch plant location is at Gravel Mountain.
Photo showing 7 international L-190 trucks, complete with Jaegar ReadyMix Concrete Machines, first installment of a large fleet at Kitimat. In early June, these were waiting for completion of batching plant installation. They were used to carry concrete directly to the new smelter, townsite or any construction in progress. Batch plant location is at Gravel Mountain.
Photo showing view looking west at south portion of Sandhill showing Gravel Screening Plant at center foreground and concrete plant and cement silos at left.
Photo showing view looking west at south portion of Sandhill showing Gravel Screening Plant at center foreground and concrete plant and cement silos at left.